Nativo Resources PLC (NTVO) · 2026-10-26
Design and Construction Engineering Contract
Nativo Resources has awarded StratumX detailed design and construction engineering work for its La Patona gold plant, moving the project from FEED into the engineering, procurement and construction stage. Phase 1 funding is stated to be secured through a non-dilutive gross revenue share arrangement with Chancery Royalty, announced on 18 September 2026.
Nativo Resources Plc (NTVO) · 2026-09-18
Project Finance & Equity Subscription Agreement
Nativo has signed a conditional funding agreement for US$3,500,000 of project finance and a £600,000 equity subscription to complete La Patona Phase 1. The finance remains subject to definitive documents, while the two equity tranches would represent approximately 17.4% of enlarged share capital.
Nativo Resources PLC (NTVO) · 2026-08-06
Gold Plant Benchmark Study & Ore Supply Analysis
Nativo Resources published internally generated, illustrative La Patona benchmark and ore-supply studies, but its anchor supply commitment remains uncontracted and grade unverified.
Nativo Resources PLC (NTVO) · 2026-07-31
Retail Offer Close
Nativo Resources PLC said its retail offer raised £43,375 before expenses through 21,687,500 new shares, taking total gross fundraising proceeds to £0.683m. Net proceeds are earmarked for working capital across primary gold mining, ore processing and tailings opportunities.
Nativo Resources PLC (NTVO) · 2026-07-28
Retail Offer
Nativo Resources has launched a retail offer of new shares at 0.2p to raise up to GBP60,000, alongside a GBP640,000 placing and subscription at the same price. The retail offer is conditional on completion of the placing and subscription.
Nativo Resources Plc (NTVO) · 2026-07-28
Placing and Subscription to Raise £640,000
Nativo Resources has raised GBP640,000 in gross proceeds through a placing and subscription at 0.2p per share, a discount of approximately 4.8%. An additional retail offer could raise up to GBP60,000 at the same price.
Nativo Resources PLC (NTVO) · 2026-07-13
Operations Update: Gold Ore Processing Plant
Nativo Resources PLC re-sequenced La Patona into three phases. Phase 1 capex is US$2.03m, with first gold targeted in Q4 2026 after project financing is completed.
Nativo Resources plc (NTVO) · 2026-06-29
Operations Update
Nativo says La Patona is construction-ready but still waiting on project financing. Commissioning and first production remain targeted for Q4 2026, while a commercial offtake offer for the plant's entire output is under consideration.