Cadence Minerals PLC (KDNC) · 2026-11-03
Azteca Hot Commissioning Complete
Cadence Minerals said DEV completed Azteca hot commissioning within the 45-day consent period and has filed the reports needed for its pending Operating Licence. The work used lower-grade accessible feed, so commissioning results are not expected to represent commercial production.
Cadence Minerals plc (KDNC) · 2026-09-28
Azteca Hot Commissioning Underway & CEO interview
DEV has begun hot commissioning at Amapá’s refurbished Azteca plant, initially at 25%–50% capacity, moving the project towards commercial production. However, concentrate cannot be sold or dispatched until commissioning succeeds and an Operating Licence is granted.
Cadence Minerals plc (KDNC) · 2026-08-27
Azteca Refurbishment Update
Cadence Minerals said Azteca refurbishment reached 97% completion against 95% planned on 22 August 2026, with commercial operations awaiting completion and an Operating Licence.
Cadence Minerals plc (KDNC) · 2026-08-10
Azteca refurbishment progresses from 77% to 87%
Cadence Minerals said Azteca refurbishment reached 87%, up from 77% and on plan, while completion remains targeted for 31 August 2026.
Cadence Minerals plc (KDNC) · 2026-06-17
Azteca Execution Update
Cadence said Azteca mobilisation is complete and refurbishment is underway on schedule. It expects the plant to be operationally ready by end-August 2026, but commercial operations still depend on the Operating Licence.